How does a shop built project work?
In our Gpi Tanks XL production hall in Groot-Ammers or at an external location, we produce tanks of up to approx. 5,000 m³. This way, we take full care of production, transport and installation for you; we handle everything from A to Z.
Once the design from our engineering team is finalized, production begins. In our production hall, we have all the modern machines and resources at our disposal to efficiently build high-quality tanks exactly according to your requirements
Production
We construct tanks layer by layer from bottom to top. Each hull section starts life in the decoiler, where the stainless steel sheet is unrolled in the correct shape. The ends are then welded together. Hull sections are then attached to one another before being passed to the stretcher where they are neatly joined together. Once the hull sections have been joined, they are welded, before returning to the stretcher for the weld seam to be smoothed out, allowing the tank to be finished more efficiently and retain its shape. The final phase, comprising grinding (if required), pickling and passivating, can then begin.
Materials
Safety and quality
We are VCA** and VCA Petrochemicals certified and are well acquainted with PGS 29 and PGS 30. We also safeguard quality with a number of other certifications, including ISO 9001, and carry out construction in accordance with NEN-EN-1090 and NEN-EN-14015. Learn more about how we treat safety and quality.
Other production methods
What our clients have to say